TEPCO staffer testifies execs put off tsunami measures at Fukushima plant

In this March 11, 2011 photo provided by Tokyo Electric Power Co., a tsunami is seen just after striking the Fukushima No. 1 nuclear plant breakwater.

TOKYO -- A Tokyo Electric Power Co. (TEPCO) employee testified in court here on April 10 that company executives decided to postpone tsunami prevention measures at the Fukushima No. 1 nuclear plant despite an assessment warning that a massive wave could hit the power station.

Three former TEPCO executives including former Vice President Sakae Muto, 67, are on trial for professional negligence causing death and injury over the Fukushima nuclear crisis triggered by the March 2011 Great East Japan Earthquake and tsunami. The TEPCO employee's statements at the trial's fifth hearing were in line with the arguments of the court-appointed attorney acting for the prosecution.

Since 2007, the male employee had been part of an internal assessment group tasked with estimating the maximum height of tsunami which could strike the Fukushima No. 1 plant.

The group commissioned a TEPCO-affiliated company to estimate the size of potential tsunami, based on a long-term assessment made by the government's Headquarters for Earthquake Research Promotion that a massive wave could be generated by a quake in the Japan Trench, including off Fukushima Prefecture. In 2008, the TEPCO subsidiary reported that tsunami as tall as 15.7 meters could hit the plant.

In the trial, the employee stated, "I thought that TEPCO should take the assessment into consideration in taking (earthquake and tsunami) countermeasures, as the assessment was supported by prominent seismologists." He said he was so confident that the utility would take action that he emailed another working group at the company, "There will definitely be major renovations at the Fukushima No. 1 and other plants."

When the employee reported the assessment result to Muto, the then vice president gave him instructions that could be interpreted as an order to prepare to build a levee. However, the employee testified that Muto later shifted policy and called for an investigation into whether the long-term tsunami risk assessment is correct rather than taking tsunami countermeasures.

"I thought they (TEPCO) would consider taking tsunami prevention measures, but they changed policy unexpectedly and I lost heart," the employee told the court.

Along with Muto, former TEPCO President Tsunehisa Katsumata and Vice President Ichiro Takekuro were slapped with mandatory indictments in February 2016 after a decision by the Tokyo No. 5 Committee for the Inquest of Prosecution. Since the trial's first public hearing, the court-appointed lawyers for the prosecution have claimed that the executives put off tsunami countermeasures even though TEPCO staff tasked with estimating the maximum height of tsunami that could strike the Fukushima plant endeavored to address the threat. The defendants have argued that they did not put off the countermeasures.

(Japanese original by Ebo Ishiyama, City News Department, and Ei Okada, Science & Environment News Department)